Wednesday 23 December 2015

Magnet Kitchens Islington | Pacy Interiors

PACY & WHEATLEY INTERIORS!


New Magnet showroom fit out began 2nd November in Islington



Week 2 progress at the Magnet store in Islington



Week 3 progress Magnet Islington



Progress continued at Magnet Islington! 
Externals, signage installed.



Week 6 progress at the Magnet store in Islington. 
We handed over on Monday, December 14th!


Wednesday 25 November 2015

Interior Refurbishment – East Sussex


Interior Refurbishment  East Sussex


The Co-op Exterior East Sussex
  • Client: The Cooperative group
  • Sector: Retail – Fire prevention works
  • Type: Schedule of rates
  • Procurement: Tender/Negotiation
  • Location: Cooperative store Winchelsea – East Sussex
  • Project Value: £17,000.00

The Co-op Interior Counter East SussexThe Co-op Interior East SussexThe Project

Pacy and Wheatley Interiors complete an Interior Refurbishment project in East Sussex. We were approved and appointed to carry out works on a rolling programme for the Cooperative group, this particular project mainly involves Fire prevention works with repairs and decoration being carried out within the retail area.
The vast amounts of existing Cooperative stores are on high streets or busy side roads and as such many of them have flats/apartments above the shop. It was found following a routine visit by a fire officer to a certain store that the fire prevention between the shop and the accommodation above was totally inadequate or non-existent. Subsequently leading to all of the Cooperative stores being surveyed and a scope of works being put together with a view to a rolling programme of fire prevention works being carried out for a total of 3 months from October this year.

The Solution

The programme of works commenced as detailed above. The works involved following on from
the scoping visits varied significantly, some stores requiring minor works and others needing store
closures with ceilings having to be removed whilst steel columns above were fire proofed to achieve
60 minutes protection.

This particular project was very challenging indeed with the need to fire proof all the steel girders
installed within the back of house area. The challenge here was that there was a very small void
above the ceiling and a myriad of cables located within the working area. The solution was to bring
in an Electrical contractor to identify and label the existing wiring that was to be kept and check and
remove the redundant wiring. The remaining wiring was then laid neatly into Galvanised trunking,
this enabled better and safer access to the steels and walls that needed to be fire proofed.
This particular store formed part of a row of shops and on closer inspection it was found that there
was no fire prevention installed between each unit meaning that if a fire started then there was no
means of stopping the fire spreading. The solution here was to install a 60 minute fire curtain
between the Cooperative store and the hair dressers salon next door so as to stop the risk of fire
spreading.

The whole of the back of house area was fully decorated and a brand new suspended ceiling installed,
the end result being a safer fire proofed area for the staff to work in along with a fresher and brighter
feel to the whole area, another successful Interior Refurbishment completed.

For further information on how we can help with your Interior refurbishment or shop fit, 
please Contact Us.

Friday 23 October 2015

2 New Updates!



We have completed another Interior refurbishment!


----------------------------------------------------------------------------------------




Thanks for the business guys...


----------------------------------------------------------------------

We also have a new van with our design on the side!




Tuesday 8 September 2015

The Yorkshire 3 Peaks Challenge. We did it!

To raise money for Bluebell Wood who provide care, respite & support to poorly children & their family and as a fun but challenging way for P&W staff and family to work as a team outside of our daily work lives. A total of 17 victims completed the challenge including a site engineer, accounts manager, project surveyors, labourer, chairman, cleaner, directors & site managers along with their family. The 25 mile walk comprised of the ascent and descent of the Yorkshire 3 Peaks from Pen-Y-Ghent, Whernside and last but certainly not least Ingleborough. We left Doncaster in a bus provided by P&W at 4am to arrive and start the walk at 7am. After a break for lunch we then tackled the last peak. P&W provided accommodation, food & drinks for all our fund raising. In return our team have so far raised over £5000 for Bluebell Wood with the total still rising.


Well done all the Pacy & Wheatley team for taking part, and succeeding in the Yorkshire peaks challenge Saturday. Great day spent with great people, with some great memories. Helping those less fortunate than ourselves through our support of the Bluebell wood children's hospice. The exact total raise is still to confirm, with sponsorship still coming in, but we will have raised over £2500.00, fantastic. Just needs some new legs now!!!!!!!


Social Media by Multi Web Services

Wednesday 26 August 2015

Interior Fit Out Contractors complete Doncaster Keepmoat

          Pacy & Wheatley Doncaster Rover Keepmoat Main Image

  • Client: Doncaster Rovers
  • Sector: Football, Directors Lounge
  • Type: Design and build
  • Procurement: Tender/Negotiation
  • Location: Keepmoat Stadium Doncaster
  • Project Value: £230,000.00

The Project

Pacy and Wheatley Interiors became involved with the remodelling and providing a modern and contemporary facility for the Directors of Doncaster Rovers which incorporated new toilet facilities bar trophy cabinet and total re model of the existing lounge box and seating area.
The existing facility opened for its first match on 1st January 2007 as a community stadium for Doncaster this had no allegiance to any sporting Doncaster body and therefore was designed the same and had no bells and whistles that a directors suite would require for a league one and certainly a championship club.
Following DRFC confirming the 99 year lease in 2012, the request in 2015 was to create a contemporary feel to the Directors lounge and bring a more relaxed area to the Directors box and rovers brand.
           Pacy & Wheatley Doncaster Rover Keepmoat Dinning Area              Pacy & Wheatley Doncaster Rover Keepmoat Seating Area

The Solution

Pacy and Wheatley proposed and option which was developed very quickly due to the new season approaching with the help of our Architect Mr Richard Taylor from ACP architects who we had worked with previously on the fitness suite within the stadium and who had designed the stadium. The design quickly progressed and started coming together with regular meetings and ideas with close liaison between ourselves and the clubs directors, the proposals and offerings had to be collated and proposed and agreed very quickly, this included everything within the design including bar designs trophy cabinets specially designed and manufactured carpets to include club Logos. New seating to the balcony with Logos within the back rest and fitted furniture, Ceiling designs and feature columns were agreed, A curved wall within the corridor to highlight the area was constructed which worked really well within the box area.
The project started and completed in 6 weeks and was complete for the first friendly game of the 2015-2016 season and was a pleasure to do the works of our home town club RTID.
This is an example of another difficult high street location completed on time and on budget to the clients full satisfaction. To discuss how we may help with your project please Contact Us.
Social Media Managed Mulit Web Services by Multi-Web-Services 


Wednesday 22 July 2015

Shop Fitting Contractors, Pacy and Wheatley Interiors, complete Magnet Inverness

Magnet Kitchen Inverness Outside



  • Client: The Magnet Group

    • Sector: Retail Park – Mixed trade and retail store
    • Type: Specified
    • Procurement: Tender
    • Location: Stadium Way Inverness
    • Project Value: £230,000.00

    The Project

    Pacy and Wheatley Interiors, specialising in shop fitting contracts, were delighted to have won the tender to fit out a new purpose built Magnet showroom in Inverness.
    The works involved the installation of a dividing Jumbo stud wall to separate the warehouse area from the retail and trade showrooms. There was also a requirement to install back of house facilities including a disabled access toilet and wash areas. We also created and fitted a staff kitchen into this section of the building. As mentioned above when we took over the building it was just an empty shell and we were commissioned to fit out the whole store which included the fitting of a new air conditioning system, new ceilings and fully decorated both externally and internally. New Kitchen product was then fitted into pre made room sets to form individual fully illuminated Kitchen sets which will be displayed to the general public. State of the art planning areas were also installed where store technicians will produce layouts of a potential new Kitchens for members of the general public, The design of these stores is very intricate and demanding and there was a need for high levels of communication and regular site meetings to ensure clarity between the many contractors involved as well as the direct trades who work for the client. H&S on the project needed to be closely monitored and regular tool box talks took place to ensure zero accidents were achieved. This was achieved which is testament to the safe and professional way in which the project was carried out.
    Tesco Express Isle Tesco Express Sidcup

    The Solution

    This particular store being situated in Inverness proved to be very challenging logistically. We had to ensure that all materials and plant were procured very thoroughly so as to avoid costly further deliveries, everything had to be carefully monitored to ensure the smooth running of the project. We also had to contend with Kitchen product shortages which meant that we had to carefully and painstakingly check all items delivered and then ensure that any shortages were fed back to the client in a very timely manner so that we could get the missing product delivered directly to site with the minimum amount of delay in order to ensure the project was completed on time in order for the store to launch in line with marketing and press releases
    Another difficult project in a demanding location completed to the clients full satisfaction.
    This is an example of another difficult high street location completed on time and on budget to the clients full satisfaction. To discuss how we may help with your project please Contact Us.
    Tesco Express bakery Tesco Express flowers
    Social Media Managed Mulit Web Services by Multi-Web-Services 

    Wednesday 10 June 2015

    Interior Refurbishment in Wakefield | West Yorkshire



    • Client: Addison Colbeck - Doncaster
    • Sector: Interiors
    • Type: Specified
    • Procurement: Tender Negotiated
    • Location: Wakefield, West Yorkshire
    • Project Value: £13,000. 00

    The Project

    We were approached by Addison Colbeck who we met at a Chamber of commerce local Construction event
    The project involved the part refurbishment of the school Restaurant. Our role within this area was to demolish the old queuing system and build 3 new Blockwork walls which formed the new queuing system, re decorate the area and re – position the existing pay stations.
    Within the main Atrium area we part demolished an existing seating area and installed a new staircase to match the existing at the other end of the Atrium. We also installed a Water supply to the newly installed server in the Atrium area and re decorated totally the new server area
    These works were completed in a 2 working week period whilst the school was closed for the Summer holidays in a very congested area but the works were well programmed work schedule.

    The Challenge

    The land was formally a petrol station which had been demolished sometime previously but left in disrepair. It also abutted the bottom of a railway line embankment which produced difficulties with Health & Safety requirements from Railtrack. The old petrol station steel pipework and drainage remained and would require making safe. Access to site was off a busy dual carriageway with a footpath being used by local school children. Utility services were present in the footpath and the site was adjacent to local shops and housing The client had let the building and certain design elements needed to be incorporated into the build program to suit the end user.


    The Solution

    Working closely with the School Caretaker and the project Manager from Addison Colbeck to ensure that P&W successfully installed all the required works, ensuring that the works were completed on time and to budget with minimum disruption to the School.
    Social Media Managed Mulit Web Services by Multi-Web-Services 

    Wednesday 27 May 2015

    Retail leisure fit out in Wakefield | West Yorkshire



    • Client: Roadside Properties/Majestic Wine
    • Sector: Commercial
    • Type: Newbuild & Fit Out
    • Procurement: Tender
    • Location: Wakefield, West Yorkshire

    The Project

    Pacy and Wheatley Retail and Leisure Design and Build shopfit project to construct a single story retail unit for the developer on an old disused site which had laid in disrepair for many years. The client had already leased the site to Majestic Wines which gave us the opportunity to offer the fit out service, which we were later awarded.
    The building would incorporate storeroom, office/kitchen and toilet facilities. The construction was made up of a steel portal frame with brick and block walls, timber rafters with a tiled roof. New road crossings to service yard and car park were required

    The Challenge

    The land was formally a petrol station which had been demolished sometime previously but left in disrepair. It also abutted the bottom of a railway line embankment which produced difficulties with Health & Safety requirements from Railtrack. The old petrol station steel pipework and drainage remained and would require making safe. Access to site was off a busy dual carriageway with a footpath being used by local school children. Utility services were present in the footpath and the site was adjacent to local shops and housing The client had let the building and certain design elements needed to be incorporated into the build program to suit the end user.

    The Solution

    A close cooperation was needed between ourselves, sub contractors and network rail to ensure the safe working of piling and steel erection. Ground bearing piles were installed using a 7m piling machine and planned installation program to ensure that no plant or materials could fall within 6m of the railway line. The steelwork and pumping of concrete for the foundations and ground floor slab were programmed in a similar manner. Mail drops to the local areas were carried out to let the local residents know of our proposed construction works. Safe access including banksman to assist the public were present when works to the highway crossings were being undertaken. Close consultation was undertaken between ourselves, the local highways department and utility companies for the crossing works and lane closures to the dual carriageway.

                 

    Key Achievements

    Excellent site management and close contact with the design team produced a quality building for the client.
    Delivery on time and in budget.
    Majestic Wine awarded Pacy and Wheatley Construction the fit out contract and further works.

    Testimonial

    Overall we are extremely pleased with the finished product and the professionaism shown by Pacy & Wheatley.
    Terry Smith, Partner, Roadside Properties Ltd.
    Social Media Managed Mulit Web Services by Multi-Web-Services